What it is

The Construction Phase Plan

A construction phase plan is a document that must record the (a) health and safety arrangements for the construction phase; (b) site rules; and (c) where relevant, specific measures concerning work that falls within one or more of the categories listed in Schedule 3 of the Regulations.

The plan must record the arrangements for managing the significant health and safety risks associated with the construction phase of a project. It is the basis for communicating these arrangements to all those involved in the construction phase, so it should be easy to understand and as simple as possible.

Must be prepared before the construction phase begins, covering the risks listed in Schedule 3 of CDM 2015.

We offer full CDM support and services

Plans & documentation

  • Construction Phase Plans (CPP)
  • Principal Contractor Risk Assessment
  • Traffic and Pedestrian Management Plans
  • Site set up and management packs
  • Health and Safety Policies

Advice & ongoing support

  • Client Support Services
  • Advice and Support for Principal Designers and Designers
  • Advice and Support for Principal Contractors and Contractors
  • Ongoing support, coaching and mentoring

Assessment & monitoring

  • Construction Fire Risk Assessments
  • Site Inspections
  • Management Audits
  • Accident and Incident Investigations
  • Construction Awareness Training

Why do you need it

Whose responsibility is the plan?

Planning the construction phase and drawing up a construction phase plan is the responsibility of:

The principal contractor

For projects involving more than one contractor. A Principal Contractor must plan, manage, monitor and coordinate health and safety during the construction phase of a project involving, or likely to involve, more than one contractor.

The contractor

For single contractor projects. A contractor must plan, manage and monitor all work carried out by themselves and their workers.

How do we deliver it

Proportionate, project-specific, easy to understand

Every project is unique, so the plan should be proportionate to it – detailed enough to meet CDM, simple enough that everyone on site can actually use it.

inspector in green safety vest
  1. We talk first

    We find out more about the project - who is involved, who has been appointed, and what information is already available.

  2. We use the information that exists

    Construction information from the Principal Designer or client helps us understand existing hazards and tells us when we need to visit the site.

  3. We visit and discuss with you

    We come to site and discuss how the project can be managed. Every project is unique, and the CPP should be proportionate and easy to understand.

  4. We produce the document

    Our professional documents include all the necessary detail required to meet the specification within Appendix 3 of the CDM Regulations.

Method Statements

Completing a method statement, step by step

Completing a method statement involves following a structured process to outline the step-by-step procedures, safety measures and controls for a specific task or activity. These are the general steps.

Identify the Task

Clearly define the task or activity that the method statement will address. Describe the scope, objectives, and any specific requirements or constraints.

Conduct a thorough risk assessment of the task to identify potential hazards and risks associated with each step. Consider environmental factors, equipment usage, materials involved, and the work environment. Make a list of all identified hazards.

Based on the identified hazards, determine appropriate control measures to mitigate or eliminate risks. Consider engineering controls, administrative controls, and personal protective equipment (PPE). Ensure compliance with relevant health and safety regulations and standards.

Break down the task into a series of clear and logical steps. Start with preparation activities, then move through the key actions required to complete the task. Include details such as tools/equipment needed, specific techniques to be used, and any safety precautions or limitations.

For each step, describe the necessary safety precautions and measures. This includes proper PPE, training requirements, safe work practices, and any specific instructions or emergency procedures.

Include emergency procedures for potential incidents or accidents that could occur during the task. Describe how to respond to different types of emergencies and provide information on emergency contacts, evacuation procedures, and first-aid measures.

Specify the required training, qualifications, or certifications for individuals carrying out the task. Ensure that the assigned personnel have the necessary skills and competence to perform their duties safely.

Seek input and feedback from relevant stakeholders, such as supervisors, safety officers, or project managers. Incorporate their suggestions and revise the method statement accordingly. Obtain necessary approvals before implementation.

Communicate the method statement to all individuals involved in the task. Ensure that everyone understands their roles and responsibilities and has access to the document. Provide any necessary training or instructions.

Regularly monitor the implementation of the method statement and review its effectiveness. Make adjustments as needed to improve safety and efficiency. Keep the document up to date with any changes in procedures or regulations.

Method statements should be specific, clear and easy to understand. They should address the unique risks and requirements of the task at hand - and be regularly reviewed and updated to reflect any changes or new information.

Starting a project and need your CDM documentation right? Let’s talk it through.